Thumb Rule of Construction Material
Thumb rule requirement of standard materials and standard calculation in high-raised building
- Steel =3 to 5 kg/sqft
- Cement =0.5bags/ sqft
- RMC =0.05 m3/sqft
- Block =12.5 nos /sqm
- Electrical cast = Rs 133/sqft
- Plumbing cost = Rs 126/sqft
- Fire fighting cost = Rs 40/sqft
- External development = Rs 94.5/sqft
- Civil works-Structure = RS 751.25/sqft
- Finishing works = RS 467.50/sqft
Thumb Rule of Cement Constant
- 200 mm in cm 1:6 =0.124Bags /sqm
- 200 mm in cm 1:4 =0.206 bags/sqm
- 150 mm in cm 1:6 =0.093 bags/sqm
- 150mm in cm 1:4 =0.144 bags/sqm
- 100 mm in cm 1:4 =0.103 bags/sqm
- Ceiling plastering =0.11 bags/sqm
- Wall plastering =0.09 bags/sqm
- Rough plastering =0.09 bags/sqm
- Duct plastering =0.09 bags/sqm
- External plastering =0.175 bags/sqm
- Lathen plastering =0.55 bags/sqm
- Stucco plaster =0.175 bags/sqm
- 100 mm plaster band =0.012 bags/rmt
- PCC 1: 4: 8 =3.4 bags/cum
- PCC 1:5:10 =2.52 bags/cum
- PCC 1:3:6 =4.2 bags/cum
- PCC 1:2:4 =6.02 bags/cum
- 230 mm brick =0.876 bags/cum
- 115 mm brickwork =0.218 bags/cum
- VDF 100 mm thick =0.82 bags/sqm
- Granolithic flooring =40 mm 0.35 bags/sqm
- Granolithic flooring =20 mm 0.28 bags/sqm
- Anti-skid =0.28 bags/sqm
- Ceramic =0.28 bags/sqm
- Vertified tile flooring =0.28 bags/sqm
- Vertified tile dado =0.27 bags/sqm
- Ceramic dado =0.27 bags/sqm
- Marble flooring =0.3 bags/sqm
- 100 mm ht marble skerting =0.027 bags/rmt
- Marble glading =0.27 bags/sqm
- Terracota tle flooring =0.3 bags/sqm
- Mangalore tile =0.3 bags/sqm
- Door frame fixing =0.17 bags/sqm
- Water proofing for sunken slab =0.23 bags/sqm
- Waterproofing for walls =0.23 bags/sqm
- Water proofing for balcony/toilets =0.65 bags/sqm
- Anti terminate treatment chemical Name is chlorpyrifos 20 %.38. Diluting 5 Lit of Chemical with 95 Lit of water and usage is 7.5 Sqm Per liter {Diluted}.
- To Provide 1” Dia hole And Deep 1 Foot
Labour Productivity Thumb Rule:-
- Brickwork
- 1 Mason 1 Men mazdoor 1.25 sqm
- 1 Women Mazdoor
- Wall Plastering
- 1 mason
- 1 Men mazdoor 10 sqm
- 1 Women Mazdoor
- Ceiling
- 1 mason
- 1 Men mazdoor 8 sqm
- 1 Women Mazdoor
- External Plastering
- 1 mason
- 1 Men mazdoor 8 sqm
- 1 Women Mazdoor
- Blockwork 8”
- 1 mason
- 1 Men mazdoor 10 sqm
- 1 Women Mazdoor
- Blockwork 6”
- 1 mason
- 1 Men mazdoor 8 sqm
- 1 Women Mazdoor
- Blockwork 4”
- 1 mason
- 1 Men mazdoor 8 sqm
- 1 Women Mazdoor
- Carpenter
- 1 Skilled
- 1 Un skilled 4 Sqm
- Bar bender
- 1 Skilled
- 1 UN skilled 200Kg
- Tile work
- 1 Mason
- 1M Mazdoor 10 Sqm
- Paint
- Painter skilled OBD 600 Sft
- Emulsion 800 Sft
- Putty 600 Sft
- Primer 800 Sft
- External Painting
- Ace-Low quality
- Apex-Medium Quality
- Apex ultima –High Quality
The Miscellaneous Thumb Rules in Construction:-
- One Sqm = 10.763Sft
- One Cum = 35.314 Cft
- One Acres = 4046.873
- Sqm = 43560.17
- Sft = 4840.019Yards
- One Cubic meter = 1000 liter
- One Meter = 3.280Feet
- One Mile = 1609.344 meter
- One Acre = 100 cent
- One ground = 2400
- Sft = 5.51 cent
- ½ ground = 2.75 cent
- One Mile = 8 Furlong
- One cement bag = 1.25 Cft
- One Forma box = 1*1*1.25 feet
For Adding 4 Liters of Water in 1 Cu.m Freshly Mixed Concrete
- The slump value will be increased by 25 mm.
- The compressive strength of concrete will be decreased by 1.5 to 2.0 N/mm2
- The shrinkage potential will be increased by 10%.
- 1/4 bag of cement will be wasted.
If the Temperature of Freshly Mixed Concrete Is Increased by 1%, Then
- 4 liters of water per cu.m will give equal slump.
- The air content will be decreased by 1%.
- The compressive strength of concrete will be decreased by 1.0 to 1.5 N/mm2.
If the Air Content of Freshly Mixed Concrete Is
- Increased by 1% then the compressive strength will be decreased by 5 %.
- Decreased by 1%, the yield will be decreased by 0.03 cu.m per 1 cu.m.
- Decreased by 1%, then the slump value will be decreased by about 12.5 mm.
- Decreased by 1%, then the durability of the concrete will be reduced by 10%.
Frequently asked questions (FAQs) you can include in your article on thumb rules for construction materials and their standard calculations:
What are thumb rules in construction?
Thumb rules in construction are simplified guidelines used by professionals to estimate quantities of materials like steel, cement, RMC, blocks, and costs associated with various aspects of building construction without detailed calculations.
How accurate are thumb rules for estimating construction materials?
Thumb rules provide a quick estimation based on average values and are generally used for preliminary planning. The accuracy may vary depending on specific project conditions and should be used with caution.
What factors should be considered when applying thumb rules?
Factors such as building type, design complexity, local construction practices, and material availability should be considered. Adjustments may be necessary based on these factors.
Can thumb rules be used for all types of construction projects?
Thumb rules are more suitable for standard and repetitive construction projects where historical data and averages can be applied. For complex or unique projects, detailed calculations by engineers are recommended.
How can thumb rules help in cost estimation?
Thumb rules provide a quick way to estimate costs for materials like steel, cement, and others based on per square foot or square meter area. This helps in budgeting and initial feasibility assessments.
Are there different thumb rules for different types of construction materials?
Yes, thumb rules can vary for different materials and tasks within construction, such as plastering, flooring, and structural elements. Each has its own set of average values for estimation.
What are the limitations of using thumb rules in construction?
Thumb rules may not account for specific site conditions, variations in material quality, design changes, or unforeseen circumstances. They are best used as initial estimates and require adjustment based on detailed project requirements.
How often should thumb rules be updated or verified?
Thumb rules should be verified and updated periodically to reflect changes in material costs, construction practices, and technology advancements affecting construction efficiency and material consumption.