12. Concrete has Two setting types

Initial Setting time – 30 min

Final Setting time – 10 hrs

13. De-Shuttering time of different RCC Members

RCC Member De-shuttering time
For columns, walls, vertical form-works 16-24 hrs.
Soffit formwork to slabs 3 days (props to be refixed after removal)
Soffit to beams props 7 days (props to refixed after removal)
Beams spanning up to 4.5m 7 days
Beams spanning over 4.5m 14 days
Arches spanning up to 6m 14 days
Arches spanning over 6m 21 days

14. Curing Period

The curing Period of RCC is 28days.